 |
Caltrain > Projects
> CEMOF
> CEMOF Notes
CALTRAIN CENTRALIZED EQUIPMENT MAINTENANCE
AND OPERATIONS FACILITY
MONITORING COMMITTEE
Jan. 25, 2006 Notes
Members Present:
Michael Blackman, Kay Gutknecht, Michael Riepe
Members Absent:
Cindy Chavez, Arthur Lloyd, Ken Yeager
Staff Present:
Steve Coleman, Rita Haskin, Tom Pollard, Joe Siino,
Jonah Weinberg, Nancy Wood, Cathi Zammit
Attendees:
Megan Doyle (District 6), Bob Guillot, David Barry, Michael Smith,
Ben Tripousis (City of San Jose)
Chair Michael Riepe called the meeting to order at 6:10 p.m.
Due to a lack of quorum, all items were provided for information only.
ORAL PETITIONS
David Barry spoke about a horn being blown last night at 1 a.m.
at the Lenzen area. Joe Siino said no work was being done on
the project. Joe will follow-up with UP on Monday to remind
them to not blow the horns at night, unnecessarily.
STAFF REPORT
Rita Haskin has no information as to member terms. This is
important because there are a limited number of terms allowed
under the bylaws. Rita clarified that if a person leaves in
the middle of their term, the person replacing them only stays
for as long as the remaining term.
Megan Doyle asked on behalf of Ken Yeager as to when this
Committee will dissolve. Tripousis said the committee will
continue to meet and discuss any issues that may arise after
CEMOF is operating.
The committee believes the bylaws need to be reopened and
changed to reflect that Ken Yeager’s and Cindy Chavez’s
appointed representatives can vote on their behalf. Chair
Riepe said that Michael Blackman, Kay Gutknecht and himself
will sit on a sub-committee to review the bylaws and
recommend changes to the full committee.
CHAIRPERSON’S REPORT
Chair Riepe reported that at the last meeting he formed a
sub-committee of Blackman, Gutknecht and himself to interview
potential members for the Arena Area vacancy. Chair Riepe
said they interviewed three people and their recommendation
is Michael Smith. When the committee has a quorum, they will
vote on the new member. Chair Riepe has also asked David
Barry, who was a potential member, to continue to attend the
committee meetings.
COMMITTEE REPORT
No action items to be reviewed from last meeting.
OLD BUSINESS
No action items to be reviewed from last meeting.
Union Pacific Screeching
The committee members haven’t noticed the noise recently.
Project Manager Joe Siino said he has not heard of any complaints
of noise but has reminded UP of the noise issue. The tie replacement
has been completed and the rail will be installed this week. They
have looked into a greaser and was told that it would not correct
the screeching problem. Siino is working with the chief engineer
to look at other options. Siino confirmed that there is no CEMOF
work being done at night.
Notification of the Neighborhoods
Gutknecht said that the neighborhoods are not being notified
of these meetings. Haskin reported that Caltrain will mail a
postcard to the entire area with the upcoming meeting dates
and also include a link that directs them to the city’s Website
for the agenda. The residents will be directed to provide their
contact information if they want to receive information in the
future. Haskin also reported that a newsletter would be
distributed in March. Doyle liked the idea of the postcard
and newsletter. Chair Riepe suggested that we notify the
homeowner’s associations with the meeting dates to put in
their newsletters.
Package C Update
Bids were opened on Dec. 20 and only one was received. The bid was
42 percent higher cost than the engineer’s estimate. Caltrain
is currently looking at re-scoping this portion of the project,
which was to include a central control facility and loading dock.
The CCF may be handled by using trailers. The downscoped project
may be able to be done with a change order and could still begin
in mid-March to early-April. The entire project should be completed
in early 2007. Siino noted that construction bids are all coming
in high do to a lot of work in the industry, increased material
costs and the lack of labor. The administrative staff will work
at Diridon. Siino said that crews will start erecting the building
on Feb. 13. Siino reported that the on-site fuel facility is in
preliminary engineering and should be built by mid-2007. Haskin
reported that trackside fueling costs an additional 12 cents per
gallon. A project timeline and progress update will be included
on each quarterly meeting agenda.
NEW BUSINESS
Presentation on the Operations Plan
Manager of Rail Equipment Steve Coleman, gave a presentation
covering operation support function of CEMOF, operational flow
path through CEMOF, service and inspection tracks, train washer
facility, yard storage tracks, maintenance building functions
and material building functions. Coleman reported that the
service inspection peaks will be from 10 a.m. – noon and 5 p.m. – 10 p.m.
Committee members voiced concern over potential noise from after-hours
inspection, train washing and load testing. The washing facility has
walls around it and the load testing site is on the backside of the
facility behind a wall because it is the biggest noise maker. Coleman
stated that the Caltrain mechanics are sensitive to neighborhood noise
issues. Material deliveries will be made on Lenzen Street, generally
by 4 p.m. Train horns will be sounded as necessary according to
Federal Railroad Administration rules.
Manager of Construction Planning Cathi Zammit, reviewed item A-18 on
the Shared Objectives regarding horn tests, which may occur late at
night. Coleman said he is working with Amtrak and consultants
regarding the operational plan, but that it is too early to say
when trains will start going into the new facility. Zammit noted
that more storage tracks are being built south of Tamien.
ANNOUNCEMENTS
Gutknecht requested the committee meet more often since the project
should be going live next year. She also feels the committee needs
to go over the operational issues in more detail. Zammit reviewed
the implementation of some of the operational Shared Objectives,
which were agreed to years ago. Some things may change from time-to-time
depending on the number of trains operating. Tripousis recommended
the committee review the operational implementation and come back
next month and discuss in detail.
Next meeting date was set for Feb. 22 at 6 p.m. The agenda will
include a discussion on the Shared Objectives, voting in a new
committee member, discussion on proposed Bylaws changes and an
update on the neighborhood notification procedure. Tripousis will
follow-up with Cindy Chavez’s office and let them know she should
attend. He also will speak with Megan Doyle about Yeager’s attendance.
Adjourned
The meeting adjourned at 8:10 p.m.
|