Caltrain to Hold Public Meetings on Electrification
Caltrain is holding a series of four public meetings to obtain public comments on
the Environmental Assessment/Draft Environmental Impact Report for the Caltrain
Electrification Program.
Caltrain has examined the technical and environmental impacts of converting its train
service from diesel-hauled to electric-powered trains throughout the entire Caltrain
corridor, which extends from San Francisco to Gilroy. Caltrain is planning to
electrify the line using an overhead catenary system. Electrification will allow
Caltrain to increase the amount of service it operates while decreasing engine noise
and environmental pollution.
The recently released environmental document presents these results for public review
and comment. For convenience, meetings will be held in four locations, as follows:
San Francisco
Thursday, April 22
6 p.m. - 8 p.m.
600 Townsend, San Francisco
Three blocks from the Caltrain station
Northern Santa Clara County
Saturday, April 24
10 a.m. - Noon
Sunnyvale Senior Community Center
550 E. Remington Drive, Sunnyvale
Southern Santa Clara County
Wednesday, April 28
6 p.m. - 8 p.m.
Morgan Hill Community Center
17000 Monterey Rd., Morgan Hill
San Mateo County
Saturday, May 1
10 a.m. - noon
Caltrain Headquarters
1250 San Carlos Ave., San Carlos
SamTrans Routes 390, 391, KX
A complete version of the environmental document,
as well as an executive summary, is available at local libraries.
Members of the public can comment on the report by attending one of the meetings.
Written and e-mailed comments also will be taken through May 25 at
electrification@caltrain.com or by
writing Caltrain Electrification, 1250 San Carlos Ave., San Carlos, CA, 94070.
For additional information about the Caltrain Electrification Program, call (650)
508-6368.
4/6/04
|