Testing for the Future

As we prepare for electrified passenger service in fall 2024, there are many testing activities that need to occur before the system and trains can be placed into service. Testing of the infrastructure includes energization of the traction power facilities and overhead wires.

Each of the new electric trainsets has to also undergo a series of tests once they arrive on Caltrain property. Learn more about the different tests and check out the recent progress below, along with weekly construction updates.

Testing Progress

Trains are being tested every night! 

Electric trains testing nightly from 10:00 pm to 4:00 am

For more information on the progress of the electric train testing, see the table below for a snapshot on how close we are to bringing passengers greener, faster and more frequent service!

Electric Train Status Graphic May 2024

 

Building the Future of Electrified Service

Watch the construction process for Caltrain Electrification in the video below.

Construction Progress

All testing complete at all stations

Weekly Updates

While all major construction is complete, there are a few remaining activities that will be occurring as we closeout the project. For the upcoming week, the activities associated with the electrification infrastructure component of Caltrain Electrification are the following. Sign up for weekly updates here.

June 15 to June 21, Caltrain will be working during the day to perform tree watering. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.   

During work hours at the 22nd Street station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287

June 15 to June 21, Caltrain will be working during the day to perform tree watering. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.  

During work hours at the Bayshore station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287

June 15 to June 21, Caltrain will be working during the day to perform tree watering. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.  

During work hours at the South San Francisco station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287

June 15 to June 21, Caltrain will be working during the day to perform tree watering. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.  

During work hours at the San Bruno station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287

June 15 to June 21, Caltrain will be working during the day to perform tree watering. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.  

During work hours at the Millbrae station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287

June 15 to June 21, Caltrain will be working during the day to perform tree watering. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.  

During work hours at the Burlingame and Broadway stations all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287

June 15 to June 21, Caltrain will be working during the day to perform tree watering. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.  

During work hours at the San Mateo, Hayward Park and Hillsdale stations all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287

June 15 to June 21, Caltrain will be working during the day to perform tree watering. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.  

During work hours at the Belmont Station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287

June 15 to June 21, Caltrain will be working during the day to perform tree watering. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.  

During work hours at the San Carlos Station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287

June 15 to June 21, Caltrain will be working during the day to perform tree watering. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.  

During work hours at the Redwood City Station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287

June 15 to June 21, Caltrain will be working during the day to perform tree watering. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

June 15 to June 21, Caltrain will be working during the day to perform tree watering. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

June 15 to June 21, Caltrain will be working during the day to perform tree watering. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.  

During work hours at the Menlo Park Station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287

June 15 to June 21, Caltrain will be working during the day to perform tree watering. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.  

During work hours at the Palo Alto and California stations all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287

June 15 to June 21, Caltrain will be working during the day to perform tree watering. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.  

Caltrain is currently testing electric trains on weeknights between San Jose and Mountain View. Testing is expected to continue until Summer 2024. Each trainset must be tested for 1,000 miles before being placed into service, which is planned for September 2024.

Testing will be conducted Monday through Friday evenings between 8 pm and 4 am with an expected 1-2 test trains per hour. Residents may hear additional noise during testing hours, including grade crossing activations and train horns. We appreciate your patience as we complete this transformational project.

During work hours at the Mountain View and San Antonio stations all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287

June 15 to June 21, Caltrain will be working during the day to perform tree watering. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.  

Caltrain is currently testing electric trains on weeknights between San Jose and Mountain View. Testing is expected to continue until Summer 2024. Each trainset must be tested for 1,000 miles before being placed into service, which is planned for September 2024.

Testing will be conducted Monday through Friday evenings between 8 pm and 4 am with an expected 1-2 test trains per hour. Residents may hear additional noise during testing hours, including grade crossing activations and train horns. We appreciate your patience as we complete this transformational project.

During work hours at the Sunnyvale and Lawrence stations all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287

June 15 to June 21, Caltrain will be working during the day to perform tree watering. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.  

Caltrain is currently testing electric trains on weeknights between San Jose and Mountain View. Testing is expected to continue until Summer 2024. Each trainset must be tested for 1,000 miles before being placed into service, which is planned for September 2024.

Testing will be conducted Monday through Friday evenings between 8 pm and 4 am with an expected 1-2 test trains per hour. Residents may hear additional noise during testing hours, including grade crossing activations and train horns. We appreciate your patience as we complete this transformational project.

During work hours at the Santa Clara station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287

June 15 to June 21, Caltrain will be working during the day to perform tree watering. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.  

Caltrain is currently testing electric trains on weeknights between San Jose and Mountain View. Testing is expected to continue until Summer 2024. Each trainset must be tested for 1,000 miles before being placed into service, which is planned for September 2024.

Testing will be conducted Monday through Friday evenings between 8 pm and 4 am with an expected 1-2 test trains per hour. Residents may hear additional noise during testing hours, including grade crossing activations and train horns. We appreciate your patience as we complete this transformational project. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287

cta

Project Benefits


See how the project serves you.

train

Curious About Electrification?


Sign up for our monthly eNewsletter.

train

Stay Aware, Stay Safe


Stay safe around the new electric trains.