Caltrain Suspends Weekend Train Service Between Millbrae and Hillsdale for Electrification Construction

On the weekends of March 25-26 and April 1-2, Caltrain will be suspending rail service between Millbrae and Hillsdale Stations to accommodate Caltrain Electrification construction and testing.   

Caltrain encourages riders to see how this change in weekend service will affect their commute and to seek alternative transit options if they would better suit their transportation needs. Weekday service will not be affected. 

Limited bus service, known as a bus bridge, will be provided to Caltrain-dependent riders traveling to or from the affected area.   

These will be the fifth and sixth of 31 weekends in 2023 in which service will be adjusted to accommodate construction and testing for electrified service, which is expected to launch passenger service in fall 2024.  

Caltrain will be running a public awareness campaign throughout the year to alert riders to potential service disruptions and provide information about the new and improved service that electrification will deliver. 

Caltrain’s historic Electrification Project is the first undertaking in North America in a generation in which diesel trains and their infrastructure components are transitioned to an electrified system. The project will improve the customer experience by increasing the number of trains, modernizing service and adding new safety elements. The new trains will feature on board displays with digital trip information, increased storage capacities, baby-changing tables, Wi-Fi and power outlets at every seat. Electrification will also help meet ambitious regional and state climate action goals by lowering greenhouse gas emissions, improving air quality and relieving traffic congestion. Additionally, electrified service will advance equity along the corridor by reducing noise and air pollution while increasing access for priority equity communities. It will also set the framework for California’s future High Speed Rail network that will run on the Caltrain corridor.  

### 

About Caltrain: Owned and operated by the Peninsula Corridor Joint Powers Board, Caltrain provides rail service from San Francisco to San Jose, with commute service to Gilroy. Serving the region since 1863, Caltrain is the oldest continually operating rail system west of the Mississippi. Looking to the future, Caltrain is set to electrify the corridor by 2024, which will reduce diesel emissions and add more service to more stations while advancing the agency’s equity goals. 

Like us on Facebook at www.caltrain.com and follow on Twitter @Caltrain

Free translation assistance is available.  

Para traducción llama al 1.800.660.4287; 如需翻譯,請電 1.800.660.4287. 

Media Contact: Dan Lieberman, 650.622.2492