Construction, Installation and Maintenance: February 11 to February 17, 2017

NOTICE

 

Construction, Installation and Maintenance: February 11 to February 17, 2017

 

Please note, information reported below is subject to change without notice. If you are a member of the media, please call 650.508.7927 to confirm any information below. For all other inquiries, please call the Construction Outreach Hotline at 650.508.7726.

 

Construction

 

San Francisco Roadway Bridges Project

 

Night/Weekend Work

There is no night or weekend work scheduled for the San Francisco Roadway Bridges Project.

Weekday Work

* In general, all weekday construction activity will occur between 7 a.m. and 5 p.m. on Monday through Friday. Neighbors may experience construction noise during this time. We apologize for the inconvenience.

 22nd Street Bridge
Monday, February 13 to Friday, February 17, crews will continue formwork and rebar installation on the bridge deck.

The closure of 22nd Street between Iowa Street and Pennsylvania began on Tuesday, April 19, 2016. During the closure, vehicular access to 22nd Street between Iowa Street and Pennsylvania Avenue will remain closed during the removal and replacement of the bridge. Detour signage will be in place to direct vehicular and pedestrian traffic during the closure.

A temporary pedestrian bridge has been installed to maintain limited pedestrian access across 22nd Street. The temporary pedestrian bridge is intended for use by Caltrain customers accessing the 22nd Street Caltrain Station.

San Carlos Transit Center Project
Night/Weekend Work

There is no night or weekend work currently scheduled at the San Carlos Transit Center Project.

Weekday Work

Monday, February 13, to Friday, February 17, crews will begin installation of the retaining wall, including grading, forming and pouring. Neighbors may experience construction noise during this time. We apologize for the inconvenience. El Camino Real traffic may also be reduced to one lane during construction activities. Work may be delayed due to adverse weather conditions.

Some parking spaces in the Caltrain parking lot and along the eastside of El Camino between Cherry and Arroyo have been permanently removed as part of the project. Caltrain customers are encouraged to park at the Belmont Caltrain Station during construction.

Background
The San Carlos Multi-Modal Transit Center Project (Transit Center) is located on the west side of the railroad corridor at the site of the existing San Carlos Caltrain Station. The Transit Center project consists of transforming the existing San Carlos Caltrain Station parking lot into a multi-modal transit center that will better serve the community by improving safety and accessibility between SamTrans fixed route bus services, Caltrain commuter rail services, local shuttles, pedestrians and bicyclists. For more information on the project, please visit www.samtrans.com/sctc.

The Transit Center project is part of the larger mixed-use transit-oriented development, the San Carlos Transit Village, which is a joint development between SamTrans and Prometheus Real Estate Group.  For information about the San Carlos Transit Village Project visit:  http://cityofsancarlos.org/planning/projects/san_carlos_transit_village/default.asp

Los Gatos Creek Bridge Replacement Project Weekly Update

Night/Weekend Work
There is no night or weekend work scheduled for the project at this time.

Weekday Work 
Monday, February 13 to Friday, February 17, crews will continue to remove vegetation and pothole utilities. Crews will also begin installation of the access road for the project. Work may be delayed due to adverse weather conditions.

Background
Caltrain, in cooperation with the City of San Jose, is preparing to replace the railroad bridge crossing at Los Gatos Creek in San Jose. The current bridge was built in 1935, and in order to maintain safe rail operations and meet current seismic safety standards, the bridge must be replaced. The project will also include installation of a tail track south of the San Jose Diridon station. The tail track will provide improved operations at the station and minimize system-wide delays. Construction is expected to be complete in early 2018.

In order to maintain regular train service, some activities will be conducted during nights and weekends, outside of normal train service hours. Neighbors may experience construction noise and light during these times. We apologize for any inconvenience this may cause. For more information on the Los Gatos Creek Bridge Replacement Project, please visit www.caltrain.com/losgatos. For questions about the project, please call the Caltrain Construction Hotline at 650.508.7726 or email lgcbridge@caltrain.com.
 

Peninsula Corridor Electrification Project

The Peninsula Corridor Electrification Project (PCEP) is a key component of the Caltrain Modernization program. The PCEP would electrify the Caltrain Corridor from San Francisco’s 4th and King Caltrain Station to approximately the Tamien Caltrain Station.

 

The primary purpose of the Project is to improve Caltrain system performance, reduce long-term environmental impact by reducing noise, improving regional air quality and reducing greenhouse gas emissions. An electrified Caltrain system would better address Peninsula commuters’ vision of increased service and improved travel times in an environmentally friendly and reliable way. This also is expected to help accommodate increase system ridership through improved system operations. 

 

San Francisco

February 13 to February 17, Caltrain will be doing work during the day to confirm soil conditions. We apologize for any inconvenience this may cause. The field team will work as quietly as possible.

 

Brisbane

February 13 to February 17, Caltrain will be doing work during the day to confirm soil conditions. We apologize for any inconvenience this may cause. The field team will work as quietly as possible.

 

South San Francisco

February 13 to February 18, Caltrain will be doing work during the day and night between 7:00 p.m. to 5:30 a.m. to confirm soil conditions, survey and locate underground utilities. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

 

During night work hours, single track work schedules may be in place for South San Francisco station.

 

San Bruno

February 13 to February 18, Caltrain will be doing work during the day and night between 7:00 p.m. to 7:45 a.m. to confirm soil conditions, survey and locate underground utilities. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

 

During night work hours, single track work schedules may be in place for San Bruno station.

 

Millbrae

February 13 to February 17, Caltrain will be doing work during the day to confirm soil conditions and remove project material. We apologize for any inconvenience this may cause. The field team will work as quietly as possible.

 

Burlingame

February 13 to February 17, Caltrain will be doing work during the day to confirm soil conditions and remove project material. We apologize for any inconvenience this may cause. The field team will work as quietly as possible.

 

San Mateo

February 13 to February 17, Caltrain will be doing work during the day to confirm soil conditions and remove project material. We apologize for any inconvenience this may cause. The field team will work as quietly as possible.

 

Belmont

No work anticipated.

 

San Carlos

No work anticipated.

         

Redwood City

No work anticipated.

 

Unincorporated San Mateo County

February 13 to February 18, Caltrain will be doing work during the day and night between 7:00 p.m. to 7:45 a.m. to confirm soil conditions, survey and locate underground utilities. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.

 

Atherton

No work anticipated.

 

Menlo Park

February 13 to February 17, Caltrain will be doing work during the day to confirm soil conditions. We apologize for any inconvenience this may cause. The field team will work as quietly as possible.

 

Palo Alto

February 13 to February 17, Caltrain will be doing work during the day to confirm soil conditions. We apologize for any inconvenience this may cause. The field team will work as quietly as possible.

 

Mountain View

February 13 to February 17, Caltrain will be doing work during the day to confirm soil conditions. We apologize for any inconvenience this may cause. The field team will work as quietly as possible.

 

Sunnyvale

February 13 to February 17, Caltrain will be doing work during the day to confirm soil conditions. We apologize for any inconvenience this may cause. The field team will work as quietly as possible.

 

Santa Clara

No work anticipated.

 

San Jose

February 13 to February 17, Caltrain will be doing work during the day to survey and locate underground utilities. We apologize for any inconvenience this may cause. The field team will work as quietly as possible.

 

For more information, please call the dedicated outreach line at 650.508.6499; visit the website at www.caltrain.com/PCEP or email calmod@caltrain.com.

Installation

Communications Based Overlay Signal System (CBOSS) Positive Train Control (PTC) Project

The CBOSS PTC Project is an advanced signal system that will equip the corridor and trains with federally-mandated safety technology and will increase system capacity to help accommodate future ridership demand.

The project will monitor and, if necessary, control train movement in the event of human error. This will increase safety by:

  • Eliminating the risk of train-to-train collisions.
  • Reducing risk of potential derailments by enforcing speed limits.
  • Providing additional safety for railroad workers on the tracks.

 

  • Improving grade crossing performance to reduce gate downtime and improve local traffic circulation.

 

The CBOSS PTC Project is also a key component of the Caltrain Modernization Program, which will electrify the Caltrain Corridor by 2020. An electrified Caltrain will be cleaner and quieter and will upgrade the system to provide faster and/or more frequent service to more stations and riders.


To implement the project, Caltrain will be identifying utilities, digging a small trench and/or boring close to the tracks to install fiber optic cable. In order to maintain daytime train service, Caltrain will be performing some of this work at night.

San Francisco

On February 11 – 12, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.

 

 

 

Brisbane

On February 11 – 12, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.

 

South San Francisco

On February 11 – 12, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.

 

San Bruno

On February 11 – 12, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.

 

Millbrae

On February 11 – 12, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.

 

Burlingame

On February 11 – 12, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.

 

San Mateo

On February 11 – 12, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.

 

Belmont

On February 11 – 12, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.

 

San Carlos

On February 11 – 12, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.

 

Redwood City

On February 11 – 12, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.

 

Unincorporated San Mateo County

On February 11 – 12, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.

 

Atherton

On February 11 – 12, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.

 

Menlo Park

On February 11 – 12, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.

 

Palo Alto

On February 11 – 12, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.

 

Mountain View

On February 11 – 12, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.

 

Sunnyvale

On February 11 – 12, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.

 

Santa Clara

On February 11 – 12, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.

 

San Jose

On February 11 – 12, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.

 

For more information, please call the dedicated outreach line at 650.508.6499; visit the website at www.caltrain.com/CBOSSPTC or email caltrainptc@samtrans.com.

Maintenance

Caltrain will perform routine maintenance at several locations next week. To avoid disruptions to service, the work will mainly take place Saturday through Friday from 8 p.m. to 6 a.m. For more information about this type of work, click here, or call 650.508.7726.

San Francisco

Monday, February 13, to Friday, February 17, crews will resurface rail between the 22nd Street and Bayshore stations. Resurfacing corrects the alignment of uneven rails to make them smooth, minimizing the jerks and bumps experienced by passengers and reducing the mechanical strain on the rails. Neighbors may experience construction noise during this time. Crews will work as quietly as possible.

 

San Francisco to San Jose

Saturday, February 11, to Friday, February 17, crews will pressure wash and perform janitorial work at Caltrain stations between the San Francisco and Tamien stations.

 

Monday, February 13, to Friday, February 17, crews will weld and grind rail at various locations between the San Francisco and Tamien stations. The welding crew uses air compressors, gas-powered generators, small power tools, electric-arc welders and propane heaters. Neighbors may experience construction noise during this time. Crews will work as quietly as possible.