Construction, Installation and Maintenance: January 21 to January 27, 2017
Please note, information reported below is subject to change without notice. If you are a member of the media, please call 650.508.7927 to confirm any information below. For all other inquiries, please call the Construction Outreach Hotline at 650.508.7726.
Construction
San Francisco Roadway Bridges Project
Night/Weekend Work
Work scheduled for January 19 to January 23 has been delayed due to weather.
There is night and weekend work planned for Thursday, January 26 to Monday, January 30. Crews will be installing the precast bridge girders. Work may be delayed depending on weather conditions.
Access to residential driveways on 22nd Street between Pennsylvania Avenue and Iowa Street may be temporarily impacted from 12 a.m. to 8 a.m. Thursday, January 26 to Monday, January 30. Crews will be delivering and unloading precast bridge girders during these times. Delivery of the girders may block access to driveways along 22nd Street for up to 15 minutes at a time. Access will not be blocked unnecessarily. Crews will be on site and will restore access as soon as possible.
Weekday Work
* In general, all weekday construction activity will occur between 7 a.m. and 5 p.m. on Monday through Friday. Neighbors may experience construction noise during this time. We apologize for the inconvenience.
22nd Street Bridge
Monday, January 23 to Friday, January 27, crews will prepare for the installation of the precast bridge girders.
The closure of 22nd Street between Iowa Street and Pennsylvania began on Tuesday, April 19, 2016. During the closure, vehicular access to 22nd Street between Iowa Street and Pennsylvania Avenue will remain closed during the removal and replacement of the bridge. Detour signage will be in place to direct vehicular and pedestrian traffic during the closure.
A temporary pedestrian bridge has been installed to maintain limited pedestrian access across 22nd Street. The temporary pedestrian bridge is intended for use by Caltrain customers accessing the 22nd Street Caltrain Station.
San Carlos Transit Center Project
Night/Weekend Work
There is night and weekend work planned for Monday, January 23 to Friday, January 27. Crews will begin work on the sidewalk, curb and gutter along El Camino Real. Neighbors may experience construction noise during this time. We apologize for the inconvenience. El Camino Real traffic may be reduced to one lane during construction activities.
Weekday Work
Monday, January 23, to Friday, January 27, crews will continue improvements to the south Caltrain parking lot. Crews will continue utility work and will begin work on the sidewalk, curb and gutter along El Camino Real.
Some parking spaces in the Caltrain parking lot and along the eastside of El Camino between Cherry and Arroyo will be removed permanently as part of the project. On-site notices will be provided at least 72 hours in advance before the removal of parking.
Background
The San Carlos Multi-Modal Transit Center Project (Transit Center) is located on the west side of the railroad corridor at the site of the existing San Carlos Caltrain Station. The Transit Center project consists of transforming the existing San Carlos Caltrain Station parking lot into a multi-modal transit center that will better serve the community by improving safety and accessibility between SamTrans fixed route bus services, Caltrain commuter rail services, local shuttles, pedestrians and bicyclists. For more information on the project, please visit www.samtrans.com/sctc.
The Transit Center project is part of the larger mixed-use transit-oriented development, the San Carlos Transit Village, which is a joint development between SamTrans and Prometheus Real Estate Group. For information about the San Carlos Transit Village Project visit: http://cityofsancarlos.org/planning/projects/san_carlos_transit_village/default.asp
Los Gatos Creek Bridge Pre-Construction Utility Work
Night/Weekend Work
There is no night or weekend work scheduled for the project at this time.
Weekday Work
There is currently no work scheduled at the Los Gatos Creek Bridge site.
For more information on the Los Gatos Creek Bridge Replacement Project, please visit www.caltrain.com/losgatos. Construction for the bridge replacement is expected to begin in Early 2016.
Peninsula Corridor Electrification Project
The Peninsula Corridor Electrification Project (PCEP) is a key component of the Caltrain Modernization program. The PCEP would electrify the Caltrain Corridor from San Francisco’s 4th and King Caltrain Station to approximately the Tamien Caltrain Station.
The primary purpose of the Project is to improve Caltrain system performance, reduce long-term environmental impact by reducing noise, improving regional air quality and reducing greenhouse gas emissions. An electrified Caltrain system would better address Peninsula commuters’ vision of increased service and improved travel times in an environmentally friendly and reliable way. This also is expected to help accommodate increase system ridership through improved system operations.
San Francisco
January 23 to January 27, Caltrain will be doing work during the day to survey and locate underground utilities. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
Brisbane
January 23 to January 27, Caltrain will be doing work during the day to survey and locate underground utilities. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
South San Francisco
January 23 to January 28, Caltrain will be doing work during the day to confirm soil conditions, survey and locate underground utilities. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
San Bruno
January 23 to January 28, Caltrain will be doing work during the day to confirm soil conditions, survey and locate underground utilities. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
Millbrae
January 23 to January 28, Caltrain will be doing day and night work to confirm soil conditions, survey and locate underground utilities. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
Burlingame
January 23 to January 28, Caltrain will be doing day and night work to confirm soil conditions, survey and locate underground utilities. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
San Mateo
January 23 to January 28, Caltrain will be doing day and night work to confirm soil conditions, survey and locate underground utilities. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
Belmont
January 25 and 26, Caltrain will be doing work overnight to confirm soil conditions, survey and locate underground utilities. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
San Carlos
January 25 and 26, Caltrain will be doing work overnight to confirm soil conditions, survey and locate underground utilities. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
Redwood City
January 25 and 26, Caltrain will be doing work overnight to confirm soil conditions, survey and locate underground utilities. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
Unincorporated San Mateo County
January 23 to January 28, Caltrain will be doing work overnight to confirm soil conditions, survey and locate underground utilities. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
Atherton
January 25 and 26, Caltrain will be doing work overnight to confirm soil conditions, survey and locate underground utilities. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
Menlo Park
January 23 to January 28, Caltrain will be doing work during the day and night to confirm soil conditions, survey and locate underground utilities. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
Palo Alto
January 23 to January 28, Caltrain will be doing work during the day and night to confirm soil conditions, survey and locate underground utilities. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
Mountain View
January 23 to January 28, Caltrain will be doing work during the day and night to confirm soil conditions, survey and locate underground utilities. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
At San Antonio station, on January 23 a single track schedule may be in place during nighttime work hours, 6:00 p.m. to 6:00 a.m.
Sunnyvale
January 23 to January 28, Caltrain will be doing work during the day and night to confirm soil conditions, survey and locate underground utilities. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
Santa Clara
No work anticipated.
San Jose
No work anticipated.
For more information, please call the dedicated outreach line at 650.508.6499; visit the website at www.caltrain.com/PCEP or email calmod@caltrain.com.
Installation
Communications Based Overlay Signal System (CBOSS) Positive Train Control (PTC) Project
The CBOSS PTC Project is an advanced signal system that will equip the corridor and trains with federally-mandated safety technology and will increase system capacity to help accommodate future ridership demand.
The project will monitor and, if necessary, control train movement in the event of human error. This will increase safety by:
- Eliminating the risk of train-to-train collisions.
- Reducing risk of potential derailments by enforcing speed limits.
- Providing additional safety for railroad workers on the tracks.
- Improving grade crossing performance to reduce gate downtime and improve local traffic circulation.
The CBOSS PTC Project is also a key component of the Caltrain Modernization Program, which will electrify the Caltrain Corridor by 2020. An electrified Caltrain will be cleaner and quieter and will upgrade the system to provide faster and/or more frequent service to more stations and riders.
To implement the project, Caltrain will be identifying utilities, digging a small trench and/or boring close to the tracks to install fiber optic cable. In order to maintain daytime train service, Caltrain will be performing some of this work at night.
San Francisco
On January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.
Brisbane
On January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.
South San Francisco
On January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.
San Bruno
On January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.
Millbrae
On January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.
Burlingame
On January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.
San Mateo
On January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.
Belmont
On January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.
San Carlos
On January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.
Redwood City
On January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.
Unincorporated San Mateo County
On January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.
Atherton
On January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.
Menlo Park
On January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.
Palo Alto
On January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.
Mountain View
On January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.
Sunnyvale
On January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.
Santa Clara
On January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.
San Jose
On January 21 – 22 and January 24 and 26, Caltrain will be conducting safety tests on the corridor as part of the final phase of implementing the Advanced Signal System Project. To test the Advanced Signal System, including the roadway crossings, a test train will run through the corridor between 9:00 p.m. and 7:00 a.m. Tests are conducted at night to avoid disruption of most of regular train service and properly record the results. Neighbors may experience standard gate crossing noise and horns during this time and we apologize for any inconvenience this may cause.
For more information, please call the dedicated outreach line at 650.508.6499; visit the website at www.caltrain.com/CBOSSPTC or email caltrainptc@samtrans.com.
Maintenance
Caltrain will perform routine maintenance at several locations next week. To avoid disruptions to service, the work will mainly take place Saturday through Friday from 8 p.m. to 6 a.m. For more information about this type of work, click here, or call 650.508.7726.
San Francisco to San Jose
Saturday, January 21, to Friday, January 27, crews will pressure wash and perform janitorial work at Caltrain stations between the San Francisco and Tamien stations.
South San Francisco to Burlingame
Monday, January 23, to Friday, January 27, crews will resurface rail between the South San Francisco and Broadway stations. Resurfacing corrects the alignment of uneven rails to make them smooth, minimizing the jerks and bumps experienced by passengers and reducing the mechanical strain on the rails. Neighbors may experience construction noise during this time. Crews will work as quietly as possible.
Millbrae to Belmont
Monday, January 23 to Friday, January 27, crews will replace ties between the Millbrae and Belmont stations. Caltrain uses several different on-track, self-propelled machines to replace cross ties, and neighbors may experience construction noise during this time. Crews will work as quietly as possible
San Jose
Monday, January 23 to Friday, January 27, crews will weld and grind rail near the San Jose Diridon Station. The welding crew uses air compressors, gas-powered generators, small power tools, electric-arc welders and propane heaters. Neighbors may experience construction noise during this time. Crews will work as quietly as possible.