Burlingame Broadway Grade Separation Project

 

To improve safety for all modes of travel, Caltrain in cooperation with the City of Burlingame is separating the train tracks from the road at Broadway. The project will reduce local traffic congestion and train horn noise, and eliminate the current hold-out rule in which only one train is allowed at the station at a time. A new Broadway Station with updated amenities will also be constructed to better serve the community.

  • Project Study Report: 2014 to 2017

  • Preliminary Engineering / Environmental Clearance: 2017 to 2020

  • Final Design/Environmental Permits: Early 2021 to Fall 2024

  • Utilities/Early Works: Fall 2024 to Early 2025

  • Construction: *2025 to 2028

*Pending funding availability 

Project Total: $316.4 Million 

Funded by Measure A and the City of Burlingame: 

  • Project Study 
  • Preliminary Engineering 
  • Final Design 
  • Environmental Permits 

Caltrain and the City of Burlingame will be communicating with residents, businesses and other interested members of the public to discuss the project in more detail. For additional questions or comments regarding this project, please call customer service at 1.800.660.4287 or email BBGS@caltrain.com